When the Schedule Slips: How to Handle Delay Notices Between a GC and a Drywall Sub in Quebec
This article is general information, not legal advice. Your contract controls. If a delay is turning into a dispute, talk to a construction lawyer.
Short version Every job gets delayed at some point, and the ones that recover are the ones where people said so early, in writing, with facts. A good delay notice names the cause, the areas affected, the effect on the schedule and what is needed to fix it. Giving one is not an accusation. It is how a schedule gets protected.
Nobody enjoys sending a delay notice. It can feel like picking a fight, or admitting defeat. In practice it is the opposite. The general contractor who hears about a problem on Tuesday can reshuffle trades. The one who hears about it on Friday is already behind.
Why do delays happen on drywall jobs?
Drywall sits in the middle of the schedule, so it catches everyone else’s delays. Trade writers list the usual suspects: incomplete work by a preceding trade, late submittals, failed inspections, owner design changes, and conditions on site (no heat, no power, wet building). We covered the pattern in our article on why drywall finishing wrecks schedules.
Sometimes the delay comes from the sub itself: a crew that is late, a product that did not arrive, a rework. Those need to be reported too.
Who is responsible?
In Quebec, the general contractor is bound to an obligation of result toward the owner, meaning the finished work has to meet the plans and standards, even where subcontractors did the work. The sub has a contract with the GC, usually not with the owner. That is why the notice chain matters: it is how a problem travels from the person who sees it to the person who has to manage it.
Whether a delay entitles anyone to extra time or money depends on its cause and on what the contract says. That is a question for the contract and, if needed, a lawyer.
How fast should you give notice?
Faster than the contract requires. The deadlines vary:
- One legal source notes that a CCDC 2 contract can require written notice within 10 working days of the start of a delay.
- Customized contracts can require notice within 48 to 72 hours.
Your subcontract may mirror either, or something different. Read the clause before the job starts, not after the delay. And if you are not sure whether something qualifies as a delay, send the heads-up anyway. A short note that turns out to be unnecessary costs nothing. A missed notice can cost a lot.
What a good notice says
Keep it short, factual and in writing. A good structure:
- What happened. One or two sentences, no blame.
- When it started. Dates matter.
- Where. The areas, floors or units affected.
- What it affects. Which activities, and the estimated effect on the schedule.
- What is needed. Access, heat, a closed inspection, a decision from the owner.
- What you are doing. Re-sequencing, moving crew to another area, adjusting the plan.
- Next update. When you will report again.
Add photos when there are any. They save a long conversation later.
Example: “Floor 2 east wing was not accessible from Monday 9 because electrical rough-in was not closed. This holds taping in that wing. We moved the crew to floor 3 and expect to lose 3 working days on floor 2 unless access is available by Wednesday. Please confirm the inspection date. Next update Thursday.”
That is a note a GC can act on.
If you are the one receiving it
- Acknowledge it, even briefly. Silence reads as agreement or indifference.
- Check the cause. Is it really the drywall sub’s issue, or upstream?
- Look for options together. Re-sequencing zones, extra crew, extended hours, temporary heat.
- Keep a log. Notices, dates, responses. Memories fade, emails do not.
- Tell the other trades who are affected, including the painters.
The GCs who handle this well usually get better subs over time, because subs learn it is safe to bring bad news early.
Most notices are avoidable
Most come from the same few causes, and most are avoidable:
- Confirm conditions before the crew arrives: heat, power, light, access, inspections closed
- Plan calendar days, not only labour days, so drying time is in the schedule
- Hold a short pre-job meeting with the finisher and painter
- Make notification a habit in both directions
- Keep a buffer in the schedule for the unplanned
A note about relationships
A delay notice can feel like a legal document. It should read like a message from a colleague. The subs that get called back on the next job are rarely the ones with zero delays. They are the ones who told you early and brought a plan.
One last thing. If you are the sub, send the notice. If you are the GC, thank the sub who sends it. That small habit is worth more than any clause in the contract.
Quick answers
- Who is responsible for a delay on a Quebec construction project?
- It depends on the cause and on the contract. In Quebec, the general contractor owes the owner a result and remains answerable for the work of its subcontractors, but delays caused by other trades, owner changes or site conditions can be handled through the contract's notice and extension provisions.
- How quickly must a delay notice be given?
- It depends on the contract. One legal source notes that a CCDC 2 contract can require written notice within 10 working days of the start of a delay, while customized contracts may require notice within 48 to 72 hours. Always read your own contract.
- What should a delay notice include?
- The date the delay began, the cause, the areas and activities affected, the estimated effect on the schedule, what is needed to resolve it, and what the sub is doing to limit the impact. Keep it factual and put it in writing.
- Should a subcontractor warn the GC even if they are not sure?
- Yes. Most subcontracts expect the sub to flag delays and deficiencies in the work before theirs. An early heads-up gives the GC options. A late surprise does not.